Summerlin Call Center Upgrade


Project Description:


Leadership

Division: Marketing
Divsion Officer: Carlos Sanchez
Department President: Ai Kwon
Department Sr. VP: Carlos Sanchez
Department VP: Mariani Riccard
Department Manager: Sato Hiroshi


Project Team:

Program Sponsor: Nancy Parker
Program Manager: Rachel Russel
Project Manager: Rachel Russell


Project Stats

Current Status: status is (R)
Project Phase: Testing
Phase % Complete: 50%
Project % Complete: 45%
Risks:
Issues:  


Delivery Dates:

Scheduled Start Date: 1-22-2024
Scheduled End Date: 7-16-2024
Target Start Date: 1-22-2024
Target End Date:8-6-2024
End Date Variance: 21 Days (-56%)


Finances

Approved Budget: $145,492
Change Budget: $0
Revised Budget: $145,492
Change Requests:
Project Actuals: $73,983
Earned Value: 0.01


Resources

Architect: Gary Rogers
Engineer: Sergey Petro
Developer: Alexander Smirn
Network: Barbara Miller
Database: Francisco Torres





Issue Notes