NT Server Removal


Project Description:


Leadership

Division: Security
Divsion Officer: Mark Hall
Department President: Antonio Lopez
Department Sr. VP: Mark Hall
Department VP: Richard Anderso
Department Manager: Kimura Shota


Project Team:

Program Sponsor: Larry Cooper
Program Manager:
Project Manager: Juan Cole


Project Stats

Current Status: status is (R)
Project Phase: Testing
Phase % Complete: 35%
Project % Complete: 85%
Risks:
Issues:  


Delivery Dates:

Scheduled Start Date: 4-15-2024
Scheduled End Date: 9-15-2024
Target Start Date: 4-15-2024
Target End Date:9-29-2024
End Date Variance: 21 Days (-13%)


Finances

Approved Budget: $2,500,000
Change Budget: $86,300
Revised Budget: $2,586,300
Change Requests:
Project Actuals: $2,572,075
Earned Value: 0.01


Resources

Architect: Brandon Ward
Engineer: Antonio Gome
Developer: Donald Baker
Network: Charles Jackson
Database: Alexey Lebedev





Issue Notes