Decommission Walden Facilities


Project Description:


Leadership

Division: Finance
Divsion Officer: Roberto Silva
Department President: JamesMadison
Department Sr. VP: Enrique Rios
Department VP: Donald Allen
Department Manager: Esposito Andre


Project Team:

Program Sponsor: Raymond Wood
Program Manager: Christian For
Project Manager: Jesse Hayes


Project Stats

Current Status: status is (Y)
Project Phase: Design
Phase % Complete: 60%
Project % Complete: 75%
Risks:
Issues:  


Delivery Dates:

Scheduled Start Date: 6-24-2024
Scheduled End Date: 9-4-2024
Target Start Date: 6-24-2024
Target End Date:10-1-2024
End Date Variance: 14 Days (-15%)


Finances

Approved Budget: $333,589
Change Budget: $0
Revised Budget: $333,589
Change Requests:
Project Actuals: $242,686
Earned Value: 0.01


Resources

Architect: Yamaguchi Hana
Engineer: Santiago Mor
Developer: Liu Yang
Network: Jose Martinez
Database: Rebecca Richardson





Issue Notes