Cito Comp not following up action items of project

Issue Description:
Cito Comp has initiated several actions on the project, but fails to follow up when their participation is needed. Examples: Security settings, admin training, screen layout, requirements confirmation, UAT testing.
Issue Resolution:
08/05: Cito Comp commented that we wanted the Minnow logo on the screen, then pushed off to August when mockups sent. Cito Comp required security settings, but has not reviewed settings document, nor responded with list of managers. Cito Comp loaded new data that caused errors, but does not accept Tomas Verde offer for admin training.


PMO Info

Project: PMO-2024-034-003
Issue Type: Process
Issue Priority: High



Issue Stats

Open Date: 9-25-2024
Close Date: 10-5-2024
Issue Open Days: 10



Status

Status: Closed
Issue Owner: Pete Buddig

No Notes Recorded For This Issue